Free tool
Free make-and-pack capacity planner
For a batch or continuous process that feeds a filling or packing line through a buffer tank. Enter the making activity, the tank and the products you pack. The WolfWyse planning engine plans the week hour by hour and shows whether the demand fits, whether making or packing is the bottleneck, and what a bigger tank or a shorter changeover would do. Free, with no sign-up. Your figures are sent to our planning engine to be planned. The names you type are not.
Loading the planner…
How to use the planner
- Load an example close to your process, or overwrite the one shown.
- Describe the making activity: what it is called, the WIP it makes, whether it runs in batches or continuously, and when it is staffed.
- Enter the capacity of the tank, hopper or store between the two activities, and what is in it on Monday morning.
- List the products the packing activity packs this week, in the order they run, with the rate, the week's demand and the changeover after each.
- Read the week. Then choose Try it on any change in the list to plan the week again with that change made.
What each input means
- Making activity
- The activity that produces the WIP: Cooking, Mixing, Blending, Baking. Give it the name your site uses.
- In batches or continuously
- Choose batches when a fixed amount is made in one go and cannot be used until the batch is finished. Choose continuously when WIP flows out at a steady rate.
- Batch size and batch time
- How much WIP one batch gives and how long it takes from start to ready. The engine counts batch time in whole hours, so 90 minutes counts as two hours.
- Rate
- For a continuous making activity, the average output rate in an hour. For a product, the amount of WIP the packing activity gets through in an hour on that product. Use average rates that already allow for stops and waste.
- Holding tank capacity
- The most WIP that can sit between the two activities. If you pack straight from the vessel the batch is made in, enter the batch size: the next batch then waits until the vessel is empty.
- In it on Monday
- WIP already in the tank when the week starts. With none, the packing activity waits for the first batch.
- Starts at, hours a day, days a week
- When each activity is staffed. Days are counted from Monday. The two activities can keep different hours, which is often where a tank earns its place.
- Week's demand
- How much of each product has to be packed this week, in the same unit as everything else.
- Changeover after
- Whole hours of changeover and cleandown after a product, before the next one can start.
How to read the week
The chart shows seven days, one column an hour. The top row is the making activity, the middle is the level in the tank against its capacity, and the bottom row is the packing activity coloured by product. Move over any hour to read what each was doing.
Waiting for WIP and tank full
Red hours on the packing row are hours it was staffed with nothing to pack. Pink hours on the making row are hours it was staffed with nowhere to put more WIP. They tell you which activity is holding the other up.
Constraint
The activity that set the pace of the week. If packing waited for WIP, the making activity is the constraint. If making stopped because the tank was full, packing is. If both happen when there is no separate tank, the missing tank is the constraint.
Time left over
Staffed hours on the packing activity after the last product is finished. That is your room for extra demand, a breakdown or a longer changeover.
What would help
The planner plans the same week again with one thing changed each time: a bigger tank, a full tank on Monday, shorter changeovers, longer hours on either activity, a bigger batch or faster rate, faster packing. It lists what each does to the finish time or the shortfall. A change that has no effect is not what limits your week, which is worth knowing before money is spent on it.
When the week does not fit, it also tries the products in other running orders, and plans the week with each product left out in turn, so you can see what has to give.
Sizing a buffer tank between making and packing
A tank between a batch process and a filling line does two jobs. It lets the filler keep running while the next batch is made, and it lets the making activity keep running while the filler is in a changeover or off shift. A tank that is too small shows up as both activities waiting on each other. A tank that is larger than it needs to be changes nothing.
To size one here, enter the tank you have or the one you are being quoted for and look for the tank in the list under What would help. If doubling it has no effect, capacity is not your problem. If it brings the finish forward, try sizes in between: the gain stops at the size where neither activity waits for the other. If you pack straight from the vessel today, enter the batch size as the capacity to see what you gain from adding a tank at all.
Finding the bottleneck between batch making and filling
Line reports usually call these two states starved and blocked. The packing activity is starved when it is waiting for WIP. The making activity is blocked when the tank is full. Add up each over the week and the larger one points at the bottleneck: a starved filler means the making side is the constraint, a blocked making activity means the filler is.
The bottleneck can move with the product. A fast format can outrun the batches while a slow one cannot keep up with them. The chart shows this hour by hour, and the readout tells you which product was running when the waiting happened.
How the plan is worked out
The planner does not calculate anything itself. It sends your figures to the WolfWyse planning engine, the one behind the production planning mode of our factory models, and draws what comes back.
The engine steps through the week an hour at a time. In each hour it checks whether each activity can run: whether it is staffed, whether it is in a changeover, whether there is WIP in the tank to pack and whether there is room in the tank for more. The tank can never go below empty or above its capacity. A batch that could not finish before the end of the shift is not started. Products run in the order you list them, and the making activity makes only the WIP the week's demand needs.
What this planner leaves out
- It has one making activity, one tank and one packing activity. A plant has many, feeding each other.
- Every product uses the same WIP, one for one. There are no recipes or bought-in ingredients.
- Stops and waste are not modelled separately. Enter average rates that already include them.
- There are no crews, shared equipment or rules about which lines can run together.
- Products run in the order you list them. The planner tries other orders when the week does not fit, but it does not sequence to minimise changeovers.
- It plans one week from a standing start.
Those are what decide what a whole plant can produce, and they are what a full factory model covers. We build that model for you in 48 hours on the same engine and test each investment you are considering against it. See how that worked for other manufacturers, or read about factory modelling for food and beverage plants.
Common questions
Is the planner free?
Yes. There is no account, nothing to install and no limit on the number of weeks you plan.
Where does the calculation run?
On the WolfWyse planning engine, the one behind the production planning mode of the factory models we build for customers. Each time you change a figure, the figures are sent to the engine and the planned week comes back. The names you type for activities and products stay in your browser.
What is WIP?
Work in progress: something one activity makes and another activity uses. Cooked sauce waiting to be filled into jars is WIP. So is blended syrup waiting for the bottling line, or baked granola waiting to be bagged.
What do waiting for WIP and tank full mean?
Waiting for WIP means the packing activity was staffed and there was nothing in the tank for it to pack. Tank full means the making activity was staffed and had nowhere to put what it would make. Whichever activity causes the other to wait is the constraint for the week.
How big should the tank be?
Big enough that neither activity waits on the other. Look at the list of changes under the plan: if doubling the tank has no effect, the tank is not what limits your week and the money is better spent elsewhere. If it finishes the week earlier, try sizes in between until the gain stops.
What happens when the week does not fit?
The planner shows how much of each product is short. Products run in the order you list them, so the ones at the end go short first. It then tries other running orders, and plans the week again with each product left out in turn, so you can see which order packs the most and what has to give.
Why does everything work in whole hours?
The planning engine steps through the week an hour at a time. Batch times are rounded up to whole hours and changeovers are entered in whole hours. A batch of an hour or less is planned as one batch an hour. That is coarse for a fast line and about right for cooking, mixing, tanks and changeovers.
Can it plan several lines, recipes or more than one week?
No. This planner covers one making activity, one tank and one packing activity for a single week. A plant with several lines feeding each other, shared tanks, recipes, crews and a longer horizon needs a full model, which is what WolfWyse builds for customers on the same engine.
Can I put the planner on my own website?
Yes. Set up a plan, choose Embed on your site and paste the code into the HTML of your page. The embedded planner opens with your plan and your readers can change every figure.